SH27 Mangawhero stream bridge
Nauhria Site Icon

SH27 Mangawhero Stream Bridge

location icon

Location:
Matamata, Waikato

client icon

Client:
Fulton Hogan

overall value icon

Overall project value:
Approx $12 million

involvement icon

Our involvement:
Rebar supply and steel fixing install

This project encompassed the build of a new 80m bridge over the Mangawhero Stream and realigning State Highway 27 to make the stretch of highway safer.

Over six months we supplied 131 ton of steel and had fixers on-site for thirty days, working at around 800kgs per person, per day.

At this time, Auckland was in lockdown so we couldn’t release our steel fixing team for install — instead, we worked on a plan b and outsourced to subcontractors, managing the process for the client.