Oceania Waterford Retirement Village
Nauhria Site Icon

Oceania Waterford Retirement Village

location icon

Location:
Hobsonville, Auckland

client icon

Client:
Aspec Construction

overall value icon

Overall project value:
Undisclosed

involvement icon

Our involvement:
Rebar supply and install

We supported the construction of this project by supplying 258 ton of steel and having our fixing team on install – when on site, they placed an average of 500kg per person per day.

The install was more difficult than usual, due to methodology required at site. The foundations install was taking longer than allowed for so it required some brainstorming between Nauhria project manager Puna, our site manager and the client to explore options on how to claw back lost time. Puna proposed prefabbing all the suspended ground floor beams in the Nauhria Reinforcing yard with approval from the project engineer to have the lap locations in the same locations. As a result, Nauhria Reinforcing started making these well ahead of install date and handover.

This solution and some hard mahi on the floor/slab reinforcing shortened the install for this floor level by up to two weeks. We also didn’t miss any further pour dates, even though the dates were initially unrealistic.

In return, Aspec gave Nauhria Reinforcing a five-star review in our NPS Survey.